Latest on the Boating Pond

Work begins on repairing the base of the boating pond

  • Work is progressing to replace the borehole pump and to repair the pond base and pipework to provide a supply of fresh water to the boating pond. 
  • The crane laying mat and the access way for the crane is now complete.
  • Joint sealing of the concrete slabs in the pond is underway. Some slab replacement of the pond base will be necessary.
  • A crane is lifting the borehole pump and rising main out of the borehole.
  • A Geotechnical survey will be carried out shortly and then develop the pump and rising main specification. 
davidartwilliamson • July 30, 2023
By Admin January 31, 2025
FoBP - Becoming a Registered Charity
By Admin January 15, 2025
Record the birds that visit Broomfield Park
By Admin January 15, 2025
Find out about the FoBP becoming a charity
By Admin January 5, 2025
Creating and managing wildlife habitats in Broomfield Park
By Co-Chairs December 3, 2024
Annual Report from the Friends of Broomfield Park
By Admin November 23, 2024
Introducing John Cole leading on community engagement on Park project
By FoBP November 17, 2024
FoBP begins a journey to become a charity
Picture of Palmers Greenery Community Cafe in Broomfield Park
By Admin October 22, 2024
Report on the Spring 2024 workshops
A group of Friends of Broomfield Park volunteers, wearing HiVis vests are standing in the park.
By Admin October 7, 2024
Broomfield Park's volunteers have won five awards for their tremendous, green-fingered efforts in the prestigious Enfield in Bloom competition.
Palmers Greenery Community cafe
By Admin October 1, 2024
Palmers Greenery Community Cafe now open Monday 11am-3pm during term time
Show More
Share by: