Latest on the Boating Pond
Work begins on repairing the base of the boating pond
- Work is progressing to replace the borehole pump and to repair the pond base and pipework to provide a supply of fresh water to the boating pond.
- The crane laying mat and the access way for the crane is now complete.
- Joint sealing of the concrete slabs in the pond is underway. Some slab replacement of the pond base will be necessary.
- A crane is lifting the borehole pump and rising main out of the borehole.
- A Geotechnical survey will be carried out shortly and then develop the pump and rising main specification.
davidartwilliamson • July 30, 2023